Projects
Hereford Solar Farm
Location: Hereford
Completion: June 2024
Scope: Full Mechanical & Electrical Delivery
Technology deployed
- Vergo 3-Portrait mounting structure
- JA Solar photovoltaic modules
- Sungrow string inverters and MV stations
Project summary
Coppertech Renewables were appointed to support the Hereford Solar Farm after the project had fallen significantly behind schedule and was at risk of missing its energisation deadline.
Our initial remit focused on recovering the module installation, however following successful delivery, we were contracted to complete the full site-wide stringing works including pulling dressing, module and string terminations and testing.
Challenges overcome
The site, located on a severe flood plain, presented multiple logistical and environmental challenges, particularly during the winter build phase. Despite these constraints, our team implemented adaptive working practices and maintained strict adherence to programme.
Through disciplined execution and strong co-ordination with the principal contractor, Coppertech successfully delivered its scope on time enabling the client to achieve energisation and avoid potential delay-related penalties.
Ready to find out more?